Main > News of the company > The company «Specstrojmontazh-Ukraine» competed construction of gas treatment complex on the plant «Dneprostal»

27/02/2012

The company «Specstrojmontazh-Ukraine» competed construction of gas treatment complex on the plant «Dneprostal»

The company  «Specstrojmontazh-Ukraine» completely finished construction of gas treatment complex of the  plant «Dneprostal» (Dnepropetrovsk). According to the contract, the specialists of the company completed assemblage of production equipment, the total weight of which is 2,750 tonnes.  The specialists of the company completed assemblage of gas treatment, heat-exchange units, station of nodulizing flue dust, chill down and non-chill down ducts, smoke pipe, air breathers and objects of shroud of arc furnace. All the works had been completed by February 2012. The control of fulfillment of the order was performed by the main contractor of the building, Italian company DANIELI.

According to Valerii Tchub, currently, only the group of specialists, the so-called start-up team, is working on the object, which is monitoring the start-up of the equipment.

The installation of unique technical equipment of gas treatment complex of the plant «Specstrojmontazh-Ukraine» had  completed by November 2011. Last autumn the equipment and systems of the gas treatment complex of the company passed cold tests, i.e. individual check-up of the systems, operation of the equipment in no-operation mode and blow down of pipe-lines.

On January, 17 2012, the hot tests of technological equipment of electrical steelmaking complex of «Dneprostal» started and the first founding was completed successfully. 100 tonnes of stock material were produced. Hot and operational tests of the enterprise will have been completed in the 1-st quarter 2012. After putting into operation the plant «Dneprostal» will become the biggest electrical steelmaking complex in the Eastern Europe. The forecasted production output in 2012 is 700,000 tonnes of steel stock material.

Reference: the plant «Dneprostal» was build according to the cutting-edge technologies. Here, for the first time in steel making process, electric arc furnace will be introduced. Installed equipment is unique for Ukraine.

The company «Specstrojmontazh-Ukraine» was founded in 1992. The company provides complex solutions for the tasks in the sphere of construction of industrial, commercial, residential and administrative objects. It has successfully implemented more than 70 projects. Among clients of the company are the following: «Severnij GOK», «Poltavkij GOK», «Stahanovskij Plant of Ferroalloys» and others.  